Lift Station (Electromechanical)
Our Projects

Lift Station (Electromechanical)

Infrastructure New Cairo, Egypt

Project Overview

Supply, installation, and testing of electromechanical works for a sewage lifting station, including pumps, generator, ATS panel, and chambers.

Key Features & Scope

  • 3 pumps: 18.5 kW each (Q=15.4 l/s, H=44.16 m) (1 duty + 2 standby).
  • 2 submersible pumps: 3.3 kW each (Q=10 l/s, H=8 m) (1 duty + 1 standby) – Grundfos.
  • Generator (Kohler) 110 kW + ATS panel 250 A.
  • Penstock 400 mm² for tank entry + basket screen 250 mm².
  • Flowmeter chamber (160 mm), valve chamber, and air valve chamber.
  • Supply, installation, and testing (commissioning-ready).

Project Gallery

Project Info

SODIC
SHAKER
Advanced Construction Technology Services
New Cairo, Egypt